The construction progress of the express delivery project is "fast" and cannot rise. Several departments in Dazhou, Sichuan have been questioned about corruption

Cover News Reporter Zeng YeChuandongbei E-commerce Express Distribution Center is one of the 44 secondary distribution points for express delivery in China. The project is located in Fuxing Town, Tongchuan District, Dazhou City, Sichuan Province

Cover News Reporter Zeng Ye

Chuandongbei E-commerce Express Distribution Center is one of the 44 secondary distribution points for express delivery in China. The project is located in Fuxing Town, Tongchuan District, Dazhou City, Sichuan Province. It covers an area of approximately 250 acres, with a planned total construction area of approximately 310000 square meters and a total investment of approximately 514 million yuan. After the completion of the project, the annual express delivery and urban-rural distribution capacity can reach 650 million pieces, providing more than 2000 job opportunities, greatly improving the efficiency of e-commerce express delivery distribution in Northeast Sichuan, and accelerating the agglomeration and development of logistics and e-commerce in Dazhou.

Shot by Zeng Ye on the scene of the program 'Sunshine Asks for Integrity'

However, due to the "fast" construction progress of the project, many express delivery items entering and leaving Dazhou have to be transferred to places such as Chongqing, Nanchong, and Suining. On the evening of October 9th, this issue was exposed in the latest live broadcast of Dazhou's "Sunshine Asking for Integrity" program. What is the crux of the problem? Why is the "Efficiency Revolution" being implemented in Dazhou not working well on this project? How to solve it? As a member of the media observation team for the program, the cover journalist conducted on-site observations.

Question:

The construction progress of express delivery projects is "fast" and cannot be improved

The Chuandongbei E-commerce Express Distribution Center project started its first phase of construction in 2021, and currently 70% of the main project has been completed. However, due to the fact that a national road within the red line of the project site has not been relocated or renovated, the construction of the fifth and sixth buildings of the e-commerce express complex cannot be started, which affects the completion acceptance of the entire Phase I project.

When the government transferred this land, we discovered this problem, "said the relevant person in charge of the project owner. Due to the fact that the Fengwu Community section of National Highway G542 has not been relocated and is still within the red line of land use, the owner and the local government have negotiated face-to-face and come up with a preliminary implementation plan: the owner will invest 51% and the government will invest 49% to relocate the section.

Renderings of Chuandongbei E-commerce Express Distribution Center Project Taken by Zeng Ye

In order to accelerate the construction of the project, the above issues were studied at the second key project construction promotion meeting of the Tongchuan District Committee in November 2020. After the headquarters meeting, it was agreed that the diversion plan proposed by the district planning center should be implemented after the district government reported to the Dazhou Transportation Bureau for approval regarding the diversion of the Fengwu Exit Ramp on the Huancheng Road (i.e. the Fengwu Community section of the national highway G542 that needs to be relocated), It is recommended that the CDB Express Distribution Center project, as the owner, receive a subsidy of 49% of the financial evaluation amount and submit it to the district government for approval.

However, the renovation plan proposed as early as November 2020 has been delayed until now and has not been implemented. The government of Tongchuan District has promised to start the relocation as soon as possible, but it has not started in the past two years. We are very anxious, "said the relevant person in charge of the project owner.

The production line of Chuandongbei E-commerce Express Distribution Center that has been put into trial operation has been taken by Zeng Ye

Blockage point:

The relocation plan for the national highway has not been finalized yet

The construction drawings they produced were sent over in July 2021, and the diversion plan was attached and also reported to the district government. However, the road construction in this plan does not comply with the regulations, with a design width of only 8.5 meters. "Zheng, a staff member of the Tongchuan District Fuxing Shuanglong Key Project Construction Task Force (hereinafter referred to as the" Task Force "), said that due to the diversion plan not meeting the relevant requirements, the Tongchuan District government did not report to the Dazhou Transportation Bureau for approval, Returned the relevant documents.

The staff of the Tongchuan District Government Office confirmed that in September 2021, the relevant documents were indeed delivered to the district government by a dedicated team, but were later returned due to "issues" with the plan. On December 29, 2021, the special team changed the plan again and sent the revised relevant documents to the district government. However, these files still have issues and have been returned once again.

Afterwards, the issues related to the relocation and renovation of the Fengwu Community section of National Highway G542 were not resolved in a timely manner, which became a "bottleneck" in the promotion of the CDB E-commerce Express Distribution Center project.

Current Situation of Fengwu Community Section on National Highway G542 (Screenshot of Program Video)

So, where exactly is the problem? If a national road needs to be relocated, it must be approved by the provincial government. "The person in charge of the special team, Hu, believes that even if it needs to be approved by the provincial government, it must follow the procedures and the relevant work must also be carried out." As a result, everyone will not move, and the relocation of this road will become a problem.

On September 28, 2022, Tongchuan District organized relevant units such as the District Transportation Bureau, the District Natural Resources Bureau (Planning Center), the District Port Logistics Center, the District Investment Promotion Center, and Fuxing Town to hold a special meeting to study the implementation plan for the ramp diversion of the Northeast Sichuan Express Distribution Center. However, the specific implementation plan has not been finalized through this meeting. Afterwards, the specialized team held multiple meetings to collect feasible proposals from multiple functional departments.

In March 2023, this project was included in the key project of "Efficiency Revolution" in Dazhou City. In July 2023, the special team organized a special meeting to promote key projects and arranged for the project to occupy the Fengwu section of G542 National Highway.

Inquiry:

Multiple departments are being thoroughly investigated in the anti-corruption process

The renovation plan for the project was being studied as early as 2020, and more than two years have passed. The relevant departments have not been able to come up with this plan. Why? In July 2021, you received a financial evaluation request and construction drawings from the owner's unit. Why did it take six months for you to say that this plan was not feasible? "During the integrity inquiry section of the program, the host questioned face-to-face, Thoroughly investigate the relevant heads of multiple functional departments involved in the exposed issues.

After multiple rounds of questioning, the crux of the problem was found - the project owner lacks funding to ensure the construction progress, the relocation of the national road involved must comply with the latest policy requirements, and the relevant departments have a weak awareness of taking the initiative and taking responsibility.

The person in charge of the special team candidly stated that although there were objective factors such as policy adjustments and information asymmetry in the specific work of project promotion, they also exposed subjective issues such as fear of difficulties and lack of promotion measures. The person in charge of the Port and Logistics Industry Development Promotion Center in Tongchuan District also admitted that they did not intervene in advance in the promotion of the project and did not start to take the lead in coordinating work until July 2023, resulting in insufficient proactive awareness. Zeng, former deputy director of the Port and Logistics Development Office in Dazhou City, stated that although they sent a project secretary to track, they lacked effective means of promotion and did not do their work properly.

As a municipal key project, the construction progress is seriously lagging behind. Anyway, our work style and efficiency are all things we should consider and reflect on. "Chen Shengtao, a member of the Standing Committee of the Tongchuan District Committee, said that the Tongchuan District Key Project Work Team is responsible for 19 key projects in the entire district, which have some difficulties and problems to some extent. Next, we will comprehensively review and do our best to help solve them. At the same time, we will pay close attention to the transformation and implementation of cadres' work style, as well as the efficiency of implementation, especially in taking the initiative to take responsibility and carry out rectification in this regard.

Statement:

Strive to solve the problem of national road relocation and renovation within three months

After identifying the root cause of the problem, how can we solve it?

We will make every effort to promote the relocation and renovation of the national highway, "said Chen Shengtao, a member of the Standing Committee of the Tongchuan District Committee, Minister of the United Front Work Department, and Chairman of the District Federation of Trade Unions. After extensive work in the early stages, the Dazhou Transportation Bureau assisted and guided Tongchuan District in implementing the relocation and renovation of the Fengwu Community section of the national highway G542. At present, a solution with better lines, less investment, and shorter time consumption has been found. Next, Tongchuan District will accelerate efforts and strive to solve road problems within three months.

At the same time, we will do everything possible to help enterprises raise project construction funds, "Chen Shengtao said. The biggest challenge facing the CDB e-commerce express delivery distribution center project is still the shortage of funds. After the stagnation of project construction, relevant departments also showed slackness, and some cadres even used it as an excuse to delay work progress. We will make good use of, make full use of, and fully utilize the development support policies of China, provinces, cities, and districts for private enterprises. After that, I will take the lead in coordinating with financial institutions, especially actively helping them find new partners to help solve financial difficulties, "Chen Shengtao said.

In the leadership statement segment, Chen Shengtao made a commitment. After 50 anti-corruption delegations voted on-site, the proportion of people who voted "satisfied" exceeded 60%. According to the program rules, the on-site evaluation passed.

If you have any news leads, please feel free to report to us. Once accepted, there will be a fee and compensation. Follow ihxdsb on WeChat for the report, QQ: 3386405712


Disclaimer: The content of this article is sourced from the internet. The copyright of the text, images, and other materials belongs to the original author. The platform reprints the materials for the purpose of conveying more information. The content of the article is for reference and learning only, and should not be used for commercial purposes. If it infringes on your legitimate rights and interests, please contact us promptly and we will handle it as soon as possible! We respect copyright and are committed to protecting it. Thank you for sharing.(Email:[email protected])